April Meeting: NBN lite, Euston Road

ARAG’s April meeting will be held this coming Thursday 13 April at 7pm. (Not the usual day of the week!)

The meeting will be held at the Cliff Noble Community Centre, 24 Suttor St, Alexandria (Corner of Renwick St). This will be our temporary home for the next few months while Alexandria Town Hall is renovated.

On the agenda:

  • NBN-Lite is coming to Alexandria
  • WestConnex, Euston Road and McEvoy Street widenings.

It has been announced that Alexandria, despite having some of the oldest and worst copper lines in Australia, is getting Fibre to the Kerb (FTTC). Come along, and find out the difference between Fibre to the Kerb and Fibre to the Home (FTTH), Fibre to the Node (FTTN) and ADSL. And find out why it matters.

And come and get an update on the planned widening of Euston Road and McEvoy Streets.

No-WestConnex Rally, NSW Parliament, 30-March

There will be a rally at NSW Parliament, Thursday March 30
4:30pm to 6pm

Speakers include Jenny Leong, and others, TBA.

The recent federal audit of WestConnex has confirmed suspicions that taxpayers’ money is being misspent on this $17+ billion toll road.

NOT ANOTHER CENT!

$1.6 billion of the subsidised federal loan for WestConnex is yet to be paid. Come along to support the demand that this loan be stopped.

McEvoy/Euston Road Carnage

Can you imagine an extra 63,000 cars per day on McEvoy Street/Euston Road?

ARAG has invited a medical expert to describe the impact, and to answer residents’ questions:

  • 7pm, Wednesday 8 March
  • Alexandria Town Hall, Garden St

Come to the next ARAG community meeting, and keep informed.

Auditor General condemns decision to tip government money into WestConnex

The Auditor General has found that the Commonwealth Government funded WestConnex, knowing that there had been no demonstration of benefits.

The decisions by both parties to provide significant support for the project were inconsistent with the advice produced by both Infrastructure Australia and DIRD. … DIRD’s advice consistently flagged that the project was in the very early stages of development and could not yet be recommended for Australian Government financial support.

The subsequent May 2014 decision to make the $500 million advance payment led to the project being approved without there being any documented analysis and advice to Ministers that the statutory criteria for giving such approvals had been met.

[W]ithout more detailed information [WestConnex] cannot be considered to have real potential when considered in the context of Infrastructure Australia’s reform and investment framework.

Further, when the project missed payment milestones, rather than corrective action being taken, the milestones were shifted to allow payments to be made anyway:

in order not to delay payments, milestones were agreed to after the respective event had already occurred or amended shortly before the payment was due to be made where New South Wales (NSW) had not met the milestone.

Although the focus of the audit was on the decision to advance money to the project, the audit did reveal that in less than two and a half years, WestConnex Stage 2 may have slipped by  as much as 18 months:

DIRD’s April 2014 advice to Ministers indicated that … construction of Stage 2 could be completed by up to two years ahead of schedule.

On 11 May 2015, the Assistant Minister for Infrastructure and Regional Development and the NSW Minister for Roads jointly announced the commencement of Stage 2 construction 18 months ahead of schedule…

On 16 September 2016, NSW had reported to DIRD that the Stage 2 main works were not expected to be complete until early 2020. This timing indicates that Stage 2 is less than six months ahead of the delivery schedule outlined in 2013.

[N]one of the 2016–17 milestones agreed in 2015 had been met…

The audit also revealed that expenditure has not always been accurately project managed:

The ANAO notes that reported expenditure information within IMS for WestConnex may be unreliable

reported expenditure for September 2016 was overstated by at least $319.4 million

initial reporting did not reflect the correct split between state and federal [funding]

Paul Fletcher, Federal Minister for Urban Infrastructure, responded that the Auditor General had not criticised the benefits.

“Nothing in this report raises any questions about WestConnex’s design, the construction program, or the benefits that WestConnex will deliver to millions of people in western and southwestern Sydney…”

The Minister is being misleading. The Auditor General did not examine the benefits. It was not his job to do so. It was the job of the Federal Government and the State Government, and they did not do so.

But now that Paul Fletcher has brought up the issue of benefits, we call for the State Government to pause all further work on WestConnex while an inquiry can be held into the true cost benefit of the project.

The full ANAO report is here.

Notes from last week’s meeting

In no particular order, here are some of the links and other material discussed at last week’s meeting:

  • Euston Road/McEvoy Street widening:More information is available here.
  • Alexandria School Senior Campus: the Development Application can be found here.  (Deadline for submissions: 23 Feb)
  • ATP: The number for reporting any issues with ATP construction work is 1800 870 549
  • Erskineville Station downgrading: the SMH article about the downgrading of the station is here.
  • The Carmageddon Video showing the road widenings is here .
  • And the Slide pack.

Auditor General’s report means Feb 14 won’t be roses for WestConnex

The Federal Auditor General’s Audit of WestConnex is due to be tabled this Tuesday, probably at around 2pm.

Once it is released, what should opponents or supporters of WestConnex be looking for?

The first thing to remember is that some things will be off limits. This is not a full audit of WestConnex.

The audit is of the Commonwealth’s decision to commit $3.5 billion in loans and grants to the project and the focus will be on the process by which that decision was made, including the information the decision relied on.

This is where things ought to get delicate for what is now the Berejiklian government, but also for the Federal Government.

If the Auditor General’s office have done their job properly, then we can expect them to identify the following issues, which are already known: Continue reading

Mass demonstration at Sydney Park

A message from WestCONnex Action Group:

Today WestConnex contractors began destroying large numbers of trees in Sydney Park on the corner of Euston and Campbell Roads.

This is an urgent appeal to WestConnex Action Group members and supporters to join a mass demonstration at the Sydney Park Camp tomorrow morning from 6am to take a stand against the clear felling of large swathes of trees and the demolition of scores of homes in St Peters at Sydney Park and surrounds.

Your support so far during this campaign has been great and is appreciated. The Sydney Park protest camp has been in operation for 116 days now and this has been a huge community effort. We now need you tomorrow and throughout this week to stand up again against WestConnex.

Despite all the evidence showing that the plans by WestConnex for the St Peters Interchange and the New M5 will be a disaster, just like the M4 East has been, Duncan Gay and the Baird government have not listened.

Their road building frenzy knows no limits – more than 800 significant trees in and around the Inner West’s largest green space, Sydney Park, will be felled in the next few weeks as works begin to widen Euston and Campbell Roads to 7 and 8 lane highways.

Premier Baird and Roads Minister Duncan Gay definitely don’t have a social license for this project. We know tens of thousands of people all around Sydney do not support this wasteful road building which will feed the corporate tollroad companies for decades to come.

Join us tomorrow morning at 6am or as early as you can at the Sydney Park Camp on the corner of Euston and Campbell Roads to stand against Baird’s vandalism.

We know there’s a better way of doing transport in this city and we are prepared to fight WestConnex for as long as it takes to stop this dirty tollroad destroying our communities.

We need everyone to stand up and say NO tomorrow morning

TAKE ACTION

THURSDAY Jan 12 from 6AM (if you can’t make it at 6, please come down as early as you can)

Corner of Euston and Campbell Roads St Peters (entry via Campbell Road – walk or drive down Campbell Road from the Princes Highway)
WestCONnex Action Group
http://www.westconnexactiongroup.org.au/

Trees Euston Rd - Total area - red to go.JPG

Music Festival to protest destruction of Sydney Park for WasteCONnex tollway

This post is sourced from http://www.westconnexactiongroup.org.au/music_festival_protest_destruction_sydney_park_westconnex_tollway to inform members and friends of the Alexandria Residents’ Action Group.

THOUSANDS of people will flock to St Peters on the October Long Weekend to protest the destruction of Sydney Park and support the anti-WestConnex blockade.

The Save Sydney Park Festival is being organised by Reclaim The Streets (RTS) and WestCONnex Action Group (WAG), and will feature multiple stages. Local acts will play everything from Chicago house to UK garage, hip hop, jungle, and drum and bass.

The family-friendly festival will be held on the Euston Road side of Sydney Park, which residents have occupied around the clock since 19 September to prevent the destruction of hundreds of trees for WestConnex. It will start at 1pm on Saturday 1 October and end at sunset.

“Where we see a park, Casino Mike sees an opportunity to sell us out,” said RTS spokesperson James Loch.

“The Baird government cares only for the profits of their major donors, but we care about every inch of our precious green space.

“If money grew on trees, you can bet they wouldn’t be cutting them down in Sydney Park.

“We will not let them trade in our beautiful park for their dirty toll road,” said Mr Loch.

“If Mike Baird gets his way, over 14,000 square metres of Sydney Park and hundreds of trees in it will be destroyed for WestConnex,” said WAG spokesperson Janet Dandy-Ward.

“They’re planning to ‘replace’ these devastating losses with what may be the world’s worst park: some ‘green space’ under the massive flyovers and unfiltered pollution stacks of the monstrous St Peters Interchange.

“The community has had enough of Mike Baird selling us out to his toll road mates, and we’re delighted to team up with Reclaim the Streets again to help stop WestConnex,” said Ms Dandy-Ward.

Contacts: James Loch 0403 601 511, Amanda Sordes 0479 101 272

Poster artwork available on request. Facebook event page: bit.ly/savesydparkfest

Reclaim The Streets has a long history of large, colourful protest festivals. View photos of previous events on Facebook at bit.ly/rtsalbum1, bit.ly/rtsalbum2, bit.ly/rtsalbum3 and bit.ly/rtsalbum4

Save Sydney Park Festival poster

Continue reading

Public Meeting: WestConnex and Central to Eveleigh

Lord Mayor Clover Moore will be holding a public meeting to discuss WestConnex and the Central to Eveleigh Precinct, on Wednesday 27 July from 6.30pm at Alexandria Town Hall, Garden Street, Alexandria.

ARAG encourages all local residents to attend. This is the future of our suburb being discussed.

Lord Mayor’s Invitation to WestConnex and Central to Eveleigh public meeting